More than $2 billion is being spent this year to repave highways, replace bridges, add new lanes and make other improvements on roads across the state. Though the roadways were clear of construction work for the past five days, due to the long Fourth of July holiday, starting at noon today the crews — and their orange cones will be back, and so will the delays.
To keep score on what's happening, here is list of the places near you and around New Jersey where road crews will be at work this summer and, in some cases, far beyond. Avoid them if you can. But if you can’t, approach with care.
• Route 1 North Brunswick bridge replacement: The Route 1 bridge will be replaced over the abandoned Sayreville Railway and local roads in the Milltown Road and the Ryders Lane interchanges north of the Route 1/130 interchange in North Brunswick Township. The construction will replace the five-span bridge with a single-span bridge. Construction will end in Summer 2011. The project will cost $24.1 million.
• Route 1&9 Saint. Paul’s Viaduct: Viaduct replacement in Hudson County over St. Paul’s Avenue will restore the deteriorated viaduct, while providing a more continuous traffic flow. The project will take an estimated four years to complete and cost $250 million. Traffic flow is continuously shifting in the area.
• Route 27 Metuchen bridge replacement: The Route 27 Bridge over Conrail in Metuchen Borough closed in April in order to safety repair the deteriorating bridge. NJDOT will provide detours for trucks and cars during the repairs. The project is scheduled for completion around October. The new bridge featuring single 12-foot lanes, 10-foot shoulders and 10-foot sidewalks in each direction. The project will cost $9 million.
• Route 36 Highlands Bridge over Shrewsbury River: NJDOT will replace bridge. The lanes will be expanded to 12-feet, with eight-feet shoulders and a median barrier. The improvements will help traffic flow and minimize seasonal impacts and diversion of traffic to local streets. The project will finish at the end of this year.
• Route 52 Causeway replacement Contract B: The bridge in Atlantic and Cape May counties will be replaced. Two fixed and two moveable bridges will be replaced by two bridges that will have two high fixed spans over Ship Channel and Beach Thorofare with new 12-foot expanded lanes, with two going in each direction. A new visitor’s center, multi-use sidewalks for bicyclists and pedestrians and several fishing piers will be provided as a part of the project by the NJDOT. The project is scheduled for completion in 2012 and cost $400 million.
• Route 70/73 Marlton Circle: The Marlton Circle will be eliminated in Burlington County. The project is scheduled for completion in winter 2011. The project will improve traffic flow and reduce accidents at the intersection. The project will cost $63 million.
• Route 295 rehabilitation projects: 25 miles of pavement will be repaired and resurfaced in Gloucester, Salem, Burlington and Camden counties. Project will switch to southbound lanes in 2010. The three projects will cost $170 million total and is expected to end in July of 2012. 17 bridge decks will be repaired and resurfaced, the acceleration and decelerations lanes will be upgraded and have new guide rails.
• Gordon’s Corner Road over Route 9: NJDOT installed a new
precast concrete bridge structure connecting Gordon’s Corner Road and Tennent Road to Morganville and Wickatunk Road over Route 9 in Monmouth County, NJDOT officials said. The bridge will have upgraded clearance and guide rails. The project costs $6.3 million and is expected to be finished by late this summer.
• Route 35/36 in Eatontown: In Eatontown Borough and Monmouth County will undergo construction that will widen highway shoulder and relocate Wall Street. New left-turn lanes along Route 35 south will replace the existing loop ramp. The project is scheduled to end in summer 2012. The project will cost $12.4 million.
• Barrier Gate Replacement: The barrier gates, warning gates and traffic signal at the Route 71 bridge over the Shark River in Avon by the Sea and Route 88 Bridge over the inland Water way in Point Pleasant will be replaced. No construction will take place during the weekend.
• Route 9 Ocean Gate Drive: The intersection between Route 9 and Ocean Gate Drive/ Korman Road in Berkely Township will see improvements. The $345,000 state-funded project will improve safety by providing left-turn lanes from the cross streets on to Route 9. All construction will take place during the day, and the project is scheduled for completion by July 2010.
• Route 9 over Route 70 bridge deck replacement: The Route 9 bridge deck over Route 70 in Toms River will be addressed by
concrete contractors to help improve conditions. NJDOT will also resurface the bridges approaching Route 9 in both directions. The project will cost $1.8 million and is scheduled for completion in November 2010.
• Route 195 Resurfacing: Route 195 will be resurfaced as a part of a $9.2 million fedearlly-funded project. Construction will mainly take place at night, with minimal daytime closures. No weekend lane closures are planned during the summer, and the project will be complete in late fall.
• Route 130 resurfacing: Roads will be resurfaced and
Pennsylvania concrete contractors will repair roadways in Burlington and Mercer counties. NJDOT officials said they plan to mill and repave asphalt sections of the road and make repair to concrete surfaces on the northbound and southbound lanes between Bordentown and Hamilton.
• Route 30 Copper River Drainage: A new drainage system will be installed to prevent the high tide from reaching local ramps. Project will cost $7.8 million, and is scheduled to be completed in November.
• Route 73/Fox Meadow Road: The $18 million project will improve roads by realigning and widening lanes on Route 73. Project is anticipated to be complete in spring 2012.
• Route 78 Newark: A 2.2 mile stretch on both sides of I-78 in Newark will be resurfaced in a $12.7 million project. The project will be completed later this year.
• Route 1/9 northbound Express lanes in Newark: Delancey Street exit ramps will be permanently closed. Express traffic heading to Delancey Street must cross over to local lanes before exiting. The $2.1 million project is scheduled for completion in July.
• Route 280 East Orange, Livingston, Newark, Orange and West Orange: Resurfacing over 35,000 square-feet. The project is scheduled for completion in March of this year and will cost $21.6 million. Overnight single and double lane closures will occur on both sides of the roadway.
• Wittpenn Bridge on Route 7 in Jersey City and Kearny: Bridge will receive structural and mechanical repairs in an $8.3 million project. The bridge will remain open to traffic weekdays from 6 a.m. to 9 p.m. but traffic shifts and lane closures may occur overnight and on weekends. The project is expected to be completed this winter.
• Route 280 Harrison and Kearny: More than two miles will be resurfaced in both directions from milepost 14.79 to 16.83. The $6.8 million project is expected to be completed in October of this year.
• Route 46 Fairfield: New acceleration lanes, deceleration lanes and ramps will be installed on the Hollywood Avenue exit off Route 46 in Fairfield. The $5.5 million project will begin the week of July 6 and is scheduled for completion in November 2011.
• Newark bridge replacement: The project will replace superstructures for Third, Fifth, Sixth and Seventh Streets as well as Roseville Avenue over New Jersey Transit’s Morristown Rail Line. The construction will cost $13.5 million and is scheduled for completion in fall 2011.
• Pulaski Skyway in Jersey City and Newark: The Skyway will be repaired in a $27 million project to redirect rain runoff away from the steel under the deck in the sections with open curb. The project began in February and is estimated to be completed by October 2011.
• Route 46 Palisades Park: The Roff Avenue Bridge, which has been closed to traffic since March, will receive major renovations by fall of this year. Roff Avenue motorists are being detoured around the construction zone.
• Route 80 Bergen and Passaic County: Road resurfacing will take place on eight miles of the eastbound side of Route 80 from west of Madison Avenue to Polifly Road. Single and double lane closures will continue until the project is completed later this summer.
• Route 17 Rutherford, East Rutherford and Hasbrouck Heights: The $14.7 million project, which began in September 2008, will be completed by August and will improve traffic flow at Highland Cross in Rutherford, Union Avenue in East Rutherford and Franklin Avenue, Malcolm Road and Williams Avenue in Hasbrouck Heights.
• The Route 3 Bridge over the Passaic River: Bridge will be replaced with construction beginning later this summer. The project area extends from Main Avenue in Clifton to the Route 17 interchange in Lyndhurst and Rutherford. Route 3 will not close during any point during construction.
• The Route 46 bridge in Dover: The bridge over the NJ TRANSIT rail line and the Rockaway River will be closed on or around July 9 for replacement. The bridge will remain closed until $50 million project is completed at the end of 2011.
• Tuckahoe Road Bridge in Estell Manor: Bridge over the Cape May Branch rail-line, which has been closed since March 15, be replaced. The $4.9 million project is scheduled for completion in late-fall 2010.
• Route 49/55 Millville City: Ramps from Route 55 southbound to Route 49 will be elongated in a $10 million project expected to be completed by fall 2011.